Testing and Integration Process
Stage 1. Preparing Servers and Virtual Machines
Responsibilities of the telecom operator or partner preparing the equipment for delivery:
Prepare a server or VM according to the requirements:
-
-
Requirements for QoE
QoE must not be installed on the SSG server.
GUI may be installed on the SSG server only for testing purposes. For production, GUI must be deployed on a separate server or VM.
GUI and QoE may be installed on the same server; in this case, hardware requirements are cumulative.
-
Ensure network connectivity between the designated servers or VMs.
Provide SSH access (port
22
) to each server over the internet or via VPN.
GUI additionally requires HTTPS access (port
443
). Each server must have internet access to install software. Check connectivity using the command:
ping vasexperts.com
Two access options are available:
Provide login and password for SSH access.
Use the ready-made script to add servers to Teleport. The script is available upon request via your account manager.
Responsibilities of VAS Experts:
Connect to the servers via SSH.
Add servers to Teleport for further support.
Stage 2. Component Installation
Installation depends on the required functionality.
Responsibilities of VAS Experts:
SSG (BRAS, NAT,
DPI): Install
SSG software on the server or VM
GUI (recommended): Install
GUI (DPIUI2) on a separate server or VM. Add all components and verify accessibility.
QoE (recommended for
DPI functionality): Install QoE on a separate server or VM. Configure storage for
DPI statistics
Set up interaction between the modules (
DPI,
GUI, QoE)
Self-installation options for the telecom operator/partner:
-
-
-
Set up interaction between the modules (
DPI,
GUI, QoE)
Stage 3. Component Configuration
Configuration depends on the required functionality.
Responsibilities of the telecom operator/partner:
Fill out the questionnaire provided by the VAS Experts manager
For NAT:
Provide a pool of public and private IP addresses
Provide the receiver’s IP address for NAT flow export (if a third-party solution is used)
For BRAS:
Configure the RADIUS server using the provided attribute dictionary
Provide information about the BRAS type (L2 or L3) and the authentication method
Configure billing responses to match the implementation scenarios
Responsibilities of VAS Experts:
For DPI:
-
-
Provide an extended QoE version for full statistics access
For NAT:
-
Configure NAT Flow export. Two options are available:
To a client-side receiver
-
For BRAS:
Configure
SSG based on the BRAS type (L2 or L3)
Collaborate with the client to configure the necessary RADIUS response attributes
Perform debugging and testing of business scenarios (e.g., financial blocking with redirect to Captive Portal, plan changes, scheduled plans)
Stage 4. Integration and Testing
Responsibilities of the telecom operator/partner:
Prepare a portion of traffic or a list of test subscribers for verification
Responsibilities of VAS Experts:
Integrate
SSG with real traffic or subscribers
Test system operability
Fix identified issues, if any
Stage 5. Transition to Production
Responsibilities of the telecom operator/partner:
Confirm that the system is functioning as required
Responsibilities of VAS Experts:
Complete setup and hand over the system for production
Provide support during the rollout phase